Ditching, drainage and some paving on tap for area roads

Graytown Road

Severe potholes on Graytown Road about one-eighth mile from Mines Road in Sedgwick.

Photo by Anne Berleant Order prints of selected PBP photos.

by Faith DeAmbrose

In Maine, first comes winter, then mud season followed closely (and sometimes overlapped) by frost heave and pothole season. It’s currently pothole season.

As the roads move, many area residents may wonder which state roads will see work in the coming year. The Maine Department of Transportation keeps a three-year improvement plan on file that shows the work slated for the state-maintained roads in the coming years—searchable and viewable in various formats at maine.gov. Below are projects scheduled for the next three years, beginning with 2019, and they include a variety of road maintenance and some paving. While 2019 projects are in the various stages of bidding and organization, projects in 2020 and 2021 are less certain.

Blue Hill

In 2019, the Route 15 Village Bridge over Mill Stream is slated for a superstructure replacement. Cost $300,000.

In years 2020 and 2021:
Bridge improvements—Falls Bridge. Cost: $7,100,000
Bicycle/Pedestrian sidewalk—South St. Cost: $500,000
Highway construction—Route 15, Sedgwick town line extending north 2.09 miles. Cost: $1,550,000
Highway paving, 1 1/4” overlay—Route 15, at Main St. extending north 4.38 miles. Cost: $1,463,824
Highway paving—Route 15, .05 of a mile south of Grindleville Rd. extending north 1.53 miles. Cost: $206,550
Drainage—Route 15, .06 of a mile south of Mill St. extending north .06 of a mile. Cost: $185,000

Brooklin

No projects in 2019

2020-2021: Culvert replacement on Route 175, .05 miles south of Flye Point. Cost: $570,000.

Brooksville — In 2019:
Drainage—ditching, grading and replacing culverts on Bagaduce Rd., at Route 15 extending north 5.75 miles to Route 176. Cost: $176,000.
Drainage—ditching, grading and replacing culverts on Coastal Rd., at the intersection of Route 175 in N. Brooksville extending south 10.02 miles to Route 175. Cost: $287,000.
Highway safety—ledge removal on Route 176, at Mines Rd. in Sedgwick extending north 3.51 miles. Cost: $35,000.

In years 2020 and 2021:
Light Capital Paving—Route 175 at Snow’s Cove Rd. extending north 14.58 miles. Cost: $588,011.
Light Capital Paving—Route 176, extending west 10.02 miles. Cost: $404,107.
Highway paving—Route 15 (Brooksville/Sedgwick), at the Deer Isle town line extending north 8.48 miles. Cost: $1,113,750.

Sedgwick — In 2019:
Drainage— Graytown Rd. culvert replacement. Cost: $40,000.
Drainage—Bagaduce Rd. ditching, grading, culverts. Cost: $176,000.
Highway safety—Route 176, culvert replacement .01 of a mile southeast of Rocks Ln. Cost: $50,000.
Highway safety—Route 172, culvert replacement .033 of a mile south of Hales Hill Rd. Cost:$60,000.

In years 2020 and 2021:
Light Capital paving—Route 172 beginning at Mines Rd. extending north 2.39 miles to Frank’s Flat. Cost: $96,389.
Light Capital paving—Route 175 at Snow’s Cove Rd. extending north 14.58 miles to Route 166. Cost: $588,011
Bridge resurfacing—Deer Isle-Sedgwick Bridge. Cost: $3,000,000.
Highway paving—Route 15 at Deer Isle town line extending north 8.48 miles. Cost: $1,113,750.

Surry

No work currently scheduled for the next three years.